Road Works Report Wk Ending 07/09/2008 - 29-08-2008

ROADWORKS REPORT WEEK ENDING: 7th September 2008

 

New Works

 

A66 Surtees Bridge Remedial Works

 

Remedial works on Surtees Bridge are to start on Monday 1st September as
detailed below:

 

The eastbound exit slip road at Thornaby Road Interchange will be closed
on the nights (20:00 - 06:00) of 1st, 2nd and 3rd September to enable
the repairs to the road surface at the top of the slip road and
replacement of lighting columns with passively safe equivalents.

 

The westbound exit slip road at Boathouse Lane interchange will be
closed on the nights of 4th and 5th September to enable the replacement
of one street lighting column with passively safe equivalent.

 

Diversion routes will be signed. The dates of the works will be subject
to weather conditions, but should certainly be completed during next
week.

 

There will also be some drainage works adjacent to the westbound entry
slip road at the Thornaby Road Interchange, which have not yet been
scheduled.  However, this work will be carried out with a coned off
safety zone, which will not require closure of any of the traffic lanes.

 

A177 Durham Road, Stockton

 

As a result of widening works on the A177 Durham Road, at the exit from
Tesco Extra, lane narrowing will be required on the southbound
carriageway from Monday 1st September for 10 weeks during off peak hours
(09:30 - 15:30).

 

Resurfacing works will be carried out towards the end of the 10 week
period and overnight closures will be required over two or three
weekends. Further details of these closures will be provided closer to
the time.

 

Norton Road, Norton

 

As a result of Direct Services carrying out 'raised entry treatment'
works on Norton Road, closures are required on Newland Avenue, Imperial
Avenue and Victoria Avenue on Sunday 31st August. Closures are also
required on Derwent Street, Grove Terrace and Windmill Terrace on Sunday
7th September for one day only. Access for pedestrians will be
maintained.

 

Newland Avenue - From it's junction with Norton Road in an easterly
direction for a distance of approximately 10 metres. The diversion route
will be via Oaklands Avenue / Westlands Avenue, Albany Road, Keithlands
Avenue / Imperial Crescent, Imperial Avenue and Norton Road.

 

Imperial Avenue - From it's junction with Norton Road in an easterly
direction for a distance of approximately 10 metres. The diversion route
will be via Imperial Crescent, Southfield Road, Gladesfield Road, Mount
Pleasant Road and Norton Road.

 

Victoria Avenue - From it's junction with Norton Road in a westerly
direction for a distance of approximately 10 metres. The diversion route
(out) will be via Mowbray Road, the back alley and Norton Road. The
diversion route in will be via Trent Street, Derwent Street and the back
alley and Norton Road.

 

Derwent Street - From it's junction with Norton Road in a westerly
direction for a distance of approximately 10 metres. The diversion route
will be via the back alley, Victoria Avenue and Norton Road.

 

Grove Terrace - From it's junction with Norton Road in an easterly
direction for a distance of approximately 10 metres. The diversion route
will be via Birkley Road, Mount Pleasant Road and Norton Road.

 

Windmill Terrace - From it's junction with Norton Road in an easterly
direction for a distance of approximately 10 metres. The diversion route
will be Windmill Terrace and Norton Road.

 

Thornaby Road, Thornaby

 

As a result of works being carried out by Northumbrian Water Ltd outside
339 Thornaby Road, temporary traffic signals will be required during
off-peak hours (09:30-15:30) on Sunday 31st August for one day only.

 

Yarm Road / Hartburn Lane Bridge

 

As a result of bridge deck waterproofing works on Yarm Road adjacent to
the junction of Yarm Road / Hartburn Lane, temporary traffic signals
will be required as existing signals will be switched off for the
duration of the works.  The works are due to commence on Monday 1st
September for duration of six weeks.

 

Ellerton Road, Stockton

 

As a result of works being carried out by Northumbrian Water Ltd outside
63 Ellerton Road, temporary traffic signals will be required on Tuesday
2nd September for one day only.

 

Copse Close, Ingleby Barwick         

 

As a result of works being carried out by Northumbrian Water Ltd outside
12 Copse Close, temporary traffic signals will be required on Tuesday
2nd September for one day only.

 

Continuing Works

 

A67 Thirsk Road

 

As a result of footpath reconstruction works by Direct Services,
temporary traffic signals are required on the A67 Thirsk Road / A1044
Green Lane Roundabout from Monday 18th August to Friday 5th September.

 

Yarm High Street

 

Northumbrian Water / Balfour Beatty works started in Yarm High Street on
7th January 2008 and are now on site working from Riverside Mews heading
towards the Catholic Church on the East side in the cobbles / parking
area. 

 

Hardwick Estate

 

Temporary road closures from 16th August, 2007, for approximately an
18-month period to allow service diversions and construction works at
High Newham Road, Waldridge Road, Whitburn Road, Whorlton Road and
Windleston Close, Hardwick.

 

Norton High Street

 

As a result of demolition and construction works to numbers 44 - 48
Norton High Street being undertaken by Wharton Construction Ltd a
temporary closure of the service road and footpath directly outside
numbers 44 - 48 is required from Monday 16th June for approximately 40
weeks. Access for residents and emergency services will be maintained. A
pedestrian diversion will be signed via a protective barrier on the road
along the High Street.

 

A1032 Newport Bridge Approach Road

 

As a result of works to the access to the Terra Site on the A1032 being
carried out by John Hellens (Contracts) Ltd, lane closures are required
from the 16th June for 12 weeks during off-peak hours (09:30 - 15:30). A
temporary central reserve closure is required for approximately 10
weeks, at the access to the Volvo / GrowHow site. Access will be left in
/ left out. Access from the south will be to 'u-turn' around the Synetix
roundabout at the end of Portrack lane.

 

Sandy Leas Lane, Elton

 

As a result of resurfacing works on Sandy Leas Lane, temporary traffic
signals will be required. Work will commence on Tuesday 26th August and
are expected to last for one week.

 

http://www.stockton.gov.uk/

If you have a local Stockton event or local Stockton news you wish to promote, please send the details via e-mail to:

Other News from Stockton

Police Join Forces to Tackle Forced Marriages
Roadworks Report Wk ending 7th December 2008
Register Your Mobile To Thwart The Thieves
Satisfaction is high, residents say
Jobs and Careers at Stockton Council

 

ukcreditcomp northeast

Tue 2 °c
Wed 3 °c
Thu 3 °c
Fri 5 °c
Sat 4 °c

Butterwick Hospice Care

Your Area | Find a business | Franchise Information | Rent Property | Fun Pages | List Cities | List Categories | Privacy Policy | Terms & Conditions